Data for a Factory -
What Is the Contribution Per Hour for Product C

question 10

Multiple Choice

Data for a factory
 Total factory cost £10,000 Total time au ailable on key resource (hours)  2,500 Contribution per unit product A £34.00 Contribution per unit product B £30.00 Contribution per unit product C £22.00 Contribution per unit product D £20.00 Hours required product A 12.0 Hours required product B 6.0 Hours required product C 6.0 Hours required product D 8.0\begin{array}{ll}\text { Total factory cost } & £ 10,000 \\\text { Total time au ailable on key resource (hours) } & 2,500 \\\text { Contribution per unit product A } & £ 34.00 \\\text { Contribution per unit product B } & £ 30.00 \\\text { Contribution per unit product C } & £ 22.00 \\\text { Contribution per unit product D } & £ 20.00 \\\text { Hours required product A } & 12.0 \\\text { Hours required product B } & 6.0 \\\text { Hours required product C } & 6.0 \\\text { Hours required product D } & 8.0\end{array}

-
What is the contribution per hour for product C


Definitions:

Analysis Period

The specific time frame over which financial or operational data is examined and analyzed for decision-making purposes.

Competitors Analysis

The evaluation of key competitors to assess their strengths, weaknesses, opportunities, and threats in comparison to one's own business.

Horizontal Analysis

A financial analysis technique that compares account balances and ratios over different periods to identify trends and changes.

Intracompany Comparison

The process of comparing similar financial information within the same company over different periods or among different departments.

Related Questions