Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed:
During March, the laboratory performed 2,000 core tests. On March 1 no direct materials (sand) were on hand. Variable manufacturing overhead is assigned to core tests on the basis of direct labour hours. The following events occurred during March:
8,600 pounds of sand were purchased at a cost of £7,310.
7,200 pounds of sand were used for core tests.
840 actual direct labour hours were worked at a cost of £8,610.
Actual variable manufacturing overhead incurred was £3,200.
-
The materials quantity variance for March is
Safe Payments
Payments that are secure and protected against fraud or theft, often through encryption and authentication measures.
Capital Deficit Balances
Situations where a company's total capital is less than zero, indicating that its liabilities exceed its assets.
Recorded Capital Account
An account on a company's balance sheet that represents the shareholders' equity invested in the business, either by contributing capital or retaining earnings.
Distribution
The process of allocating assets, such as cash dividends or stock shares, to shareholders as part of the earnings generated by a company.
Q1: <br>The Economic order quantity (EOQ) is<br><br>A)1100 units.<br>B)1500
Q4: What was the variable overhead efficiency variance
Q13: Target costing is used by many Japanese
Q20: Tuberculosis (TB) is most often found in
Q22: One criticism of the payback method is
Q26: Professional certification exams for advanced practice nurses
Q28: Management accounting is governed by generally accepted
Q34: Target costing may not be implemented if
Q52: The North Division of Barter Company makes
Q61: <br>The labour efficiency variance for March is<br><br>A)£480