Data Co enters into a two-year contract with a customer to build a data centre in exchange for consideration of €1m. Data Co incurs incremental costs to obtain the contract and costs to fulfil the contract that are recognised as assets and amortised over the expected period of benefit.
The economy subsequently deteriorates, and the parties agree to renegotiate the pricing in the contract, resulting in a modification of the contract terms.
The remaining amount of consideration to which Data Co expects to be entitled is €650,000. The carrying value of the asset recognised for contract costs is €600,000. An expected cost of €150,000 would be required to complete the data centre.
How should Data Co account for the asset after the contract modification?
MS DOS
Short for Microsoft Disk Operating System, an operating system for x86-based personal computers mostly used in the 1980s and early 1990s.
Cultural Backgrounds
The various elements that define individuals' identities and perspectives, including race, ethnicity, traditions, and social norms.
Learning Styles
The preferred methods or ways in which individuals learn best, often categorized into visual, auditory, and kinesthetic types.
Engage
To occupy, attract, or involve someone's interest or attention; alternatively, to cause someone to become involved in a conversation or activity.
Q3: The process of evaluating an environment to
Q6: According to the statistics provided by the
Q8: Peter Pontificator is proposing to purchase a
Q16: When traditional absorption costing is employed, which
Q16: Parsons Limited was involved in a
Q19: What conditions are likely to exist when
Q20: Which is not a reason for allocating
Q24: Which of the following statements in relation
Q27: The contractually agreed sharing of control over
Q39: Miss Jean, a school psychologist, administers a