A project consists of five activities.Naturally,the paint mixing precedes the painting activities.Also,both ceiling painting and floor sanding must be done prior to floor buffing. A project consists of five activities.Naturally,the paint mixing precedes the painting activities.Also,both ceiling painting and floor sanding must be done prior to floor buffing.   ​  a.Construct the PERT/CPM network for this problem. b.What is the expected completion time of this project? c.What is the probability that the project can be completed within nine hours? ​
a.Construct the PERT/CPM network for this problem.
b.What is the expected completion time of this project?
c.What is the probability that the project can be completed within nine hours?


Definitions:

Agency

A relationship between two parties in which one party, the agent, is authorized to act on behalf of another party, the principal, in business transactions.

Agreement

One of the four elements necessary for a contract; consists of an offer made by one party, the offeror, and the acceptance of the offer by another party, the offeree.

Agent

Describes a person or entity authorized to act on behalf of another, known as the principal, in dealings with third parties.

Principal

In a contractual or fiduciary relationship, the principal is the party who authorizes an agent to act on their behalf.

Related Questions