A project has the following activities,precedence relationships,and time estimates in weeks:
A project has the following activities,precedence relationships,and time estimates in weeks: ​   ​  a.Compute the expected time and variance for each activity. b.Determine the critical path and the expected duration of the project. c.What is the probability that the project will take longer than 56 weeks to complete?
a.Compute the expected time and variance for each activity.
b.Determine the critical path and the expected duration of the project.
c.What is the probability that the project will take longer than 56 weeks to complete?


Definitions:

Funded Studies

Research projects that receive financial support from government agencies, organizations, or private entities to conduct their investigations.

Unfunded Studies

Research projects that do not receive financial support from external sources such as governments, institutions, or private donors.

Norman Triplett

A psychologist known for conducting one of the earliest experiments in social psychology about the effects of competition on performance.

Racing Cyclists

Athletes who specialize in competitive cycling, often participating in races that test speed, endurance, and strategic skill on various terrains.

Related Questions