A project consists of five activities.Naturally,the paint mixing precedes the painting activities.Also,both ceiling painting and floor sanding must be done prior to floor buffing.
a.Construct the PERT/CPM network for this problem.
b.What is the expected completion time of this project?
c.What is the probability that the project can be completed within nine hours?