Completion Time (From Start to Finish)of a Building Remodeling Project

question 69

Multiple Choice

Completion time (from start to finish) of a building remodeling project is normally distributed with a mean of 200 work-days and a standard deviation of 10 work-days.To be 99% sure that we will not be late in completing the project, we should request a completion time of _______ work-days.

Understand the concept of employment discrimination and its primary remedies.
Recognize the purpose and design of Affirmative Action Plans.
Identify employment practices that may result in disparate impact discrimination.
Comprehend the legal liabilities of employers regarding racial harassment in the workplace.

Definitions:

Double-Acting Hydraulic

A hydraulic cylinder or system that allows for fluid flow and consequent movement in two directions, enabling both extension and retraction actions.

Compression

The reduction in volume and increase in pressure of air or fuel mixture within an engine cylinder.

Jounce

Upward movement of a wheel that compresses the spring.

Rebound

The release of stored energy from a spring. When a wheel and tire move downward over uneven road conditions it is called rebound.

Related Questions