During the Most Recent Month at Hybarger Corporation, Queue Time

question 149

Essay

During the most recent month at Hybarger Corporation, queue time was 3.0 days, inspection time was 0.8 day, process time was 2.8 days, wait time was 11.8 days, and move time was 0.6 day.
Required:
a. Compute the throughput time.
b. Compute the manufacturing cycle efficiency (MCE).
c. What percentage of the production time is spent in non-value-added activities?
d. Compute the delivery cycle time.


Definitions:

Mass Entertainment

Forms of entertainment designed to appeal and be accessible to a large audience, including movies, television, concerts, and sporting events.

Corporate Consolidation

The process where companies merge or are acquired, leading to a reduction in the number of companies in an industry and often increasing the market power of the remaining firms.

Work Force

The total number of a country's population who are employed or actively seeking employment.

Union Movement

A social and political movement that advocates for the rights and interests of workers, often through the formation and operation of labor unions.

Related Questions