When arranging actors and objects on a sequence diagram, it is nice to list them _____.
Active Participation
Engagement in an activity or process with full involvement and contribution, rather than remaining passive or disengaged.
Evaluated
The process of examining something systematically to determine its merit, value, or significance based on established criteria.
Monitored
Being watched, checked, or tracked, especially for progress or compliance.
Viability
The capability of being successful or effective; the ability to exist, grow, or develop.