Nancy,a Project Manager,has Identified Some Potential Risks with a Form

question 80

True/False

Nancy,a project manager,has identified some potential risks with a form creating package that is being used for the first time.The developer who is using this form creating package is new to that package,although she has been with the company for several years and has been recognized for outstanding development skills.Nancy should rate this as a high risk and immediately drop the forms creation package from this project.