What Is the Earliest Possible Completion Time for a Job

question 38

Multiple Choice

What is the earliest possible completion time for a job whose order-requirement digraph is shown below? What is the earliest possible completion time for a job whose order-requirement digraph is shown below?   A)  27 minutes B)  17 minutes C)  21 minutes D)  48 minutes