Table 31
Time (Weeks) -Using Table 3

question 122

Multiple Choice

Table 3.1
Time (weeks)
 Activity  Immediate  Predecessor(s)   Most  Optimistic  Most  Likely  Most  Pessimistic  A 1123 B  A 2412 C  A 123 D  B 678 E  B,C 101214 F  D 234 G  E,F 1515 H  A 2514\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Most } \\\text { Optimistic }\end{array} & \begin{array} { c } \text { Most } \\\text { Likely }\end{array} & \begin{array} { c } \text { Most } \\\text { Pessimistic }\end{array} \\\hline \text { A } & - 1 & 1 & 2 & 3 \\\text { B } & \text { A } & 2 & 4 & 12 \\\text { C } & \text { A } & 1 & 2 & 3 \\\text { D } & \text { B } & 6 & 7 & 8 \\\text { E } & \text { B,C } & 10 & 12 & 14 \\\text { F } & \text { D } & 2 & 3 & 4 \\& & & & \\\text { G } & \text { E,F } & 1 & 5 & 15 \\\text { H } & \text { A } & 2 & 5 & 14 \\\hline\end{array}
-Using Table 3.1,what is the earliest expected time of completion of the whole project?


Definitions:

Indirect Labor

Labor costs associated with support work that cannot be directly linked to the production of goods or services, such as maintenance and supervision.

Manufacturing Overhead

All indirect costs associated with the manufacturing process, excluding direct materials and direct labor costs.

Work in Process

Inventory that includes goods in the process of being manufactured but are not yet completed.

Manufacturing Overhead

Indirect production costs that cannot be directly attributed to specific units produced, such as utilities and rent for the production facility.

Related Questions