Table 33 -Using Table 3

question 70

Multiple Choice

Table 3.3
 Activity  Immediate  Predecessor(s)   Time  (weeks)   A 3 B 3 C 3 D  B 4 E  A,C 4 F  B 4 G  H  E 5 I  E 5\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 3 \\\text { B } & \cdots & 3 \\\text { C } & \cdots & 3 \\\text { D } & \text { B } & 4 \\\text { E } & \text { A,C } & 4 \\\text { F } & \text { B } & 4 \\\text { G } & & \\\text { H } & \text { E } & 5 \\\text { I } & \text { E } & 5 \\\hline\end{array}
-Using Table 3.3,what is the minimum number of activities that would have to be delayed in order to cause an increase in the project's earliest completion date?


Definitions:

Overestimate

To assess a value or number as greater than it actually is.

Underestimate

To judge something below its actual value, size, quantity, or importance, often leading to insufficient preparation or understanding.

Chronic Sleep Deprivation

A condition resulting from not obtaining adequate sleep over a prolonged period, affecting physical and mental health.

Immune System

The complex network of cells, tissues, and organs that work together to defend the body against disease and infection.

Related Questions