Table 35 -Using Table 3

question 72

Multiple Choice

Table 3.5
 Activity  Immediate  Predecessor(s)   Time  (weeks)   A 6 B 3 C  A,B 2 D  A 6 E  C 2 F  D,E 2 G  C 8\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 6 \\\text { B } & \cdots & 3 \\\text { C } & \text { A,B } & 2 \\\\\text { D } & \text { A } & 6 \\\text { E } & \text { C } & 2 \\\text { F } & \text { D,E } & 2 \\\text { G } & \text { C } & 8 \\\hline\end{array}
-Using Table 3.5,what is the critical path of this project?


Definitions:

Intentions

Plans or commitments to carry out a particular action in the future.

Nonverbal Communication

The process of conveying a message or information without the use of spoken language, including through gestures, facial expressions, posture, and other visual cues.

Paralanguage

Voice effects that accompany language and convey meaning. These include vocalizations such as giggling, groaning, or sighing, as well as voice qualities such as pitch and tempo.

Gesture-Call System

A communication method involving a combination of gestures and vocalizations used by primates, including humans, to convey messages or express needs.

Related Questions