Table 38 -Using Table 3

question 11

Multiple Choice

Table 3.8
 Activity  Immediate  Predecessor(s)   Time  (weeks)   A 3 B 4 C A,B5 D  A 6 E C4 F D,E2\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 3 \\\text { B } & \cdots & 4 \\\text { C } & A , B & 5 \\\text { D } & \text { A } & 6 \\\text { E } & \mathrm { C } & 4 \\\text { F } & \mathrm { D } , \mathrm { E } & 2 \\\hline\end{array}
-Using Table 3.8,what is the critical path of the above project?


Definitions:

Demand Curve

A graphical representation showing the relationship between the price of a good or service and the quantity demanded, typically sloping downward from left to right.

Willingness To Pay

The maximum amount an individual is prepared to spend to procure a good or service or to avoid something undesirable.

Consumer Surplus

The split between the total amount consumers are prepared to spend on a good or service and the actual amount they spend.

Demand Curve

A diagram that displays the connection between the cost of a commodity and the level of demand for it within a set timeframe.

Related Questions