Table 7.1
A toy company uses a kanban system to make a metal fastener that is a component of several toys. The waiting time for a container of the fasteners during production is 0.25 day; average processing time is 0.15 day per container. Each container holds 200 fasteners. The company uses 2000 fasteners a day in the production of its product.
-Use the information in Table 7.1.Using an efficiency factor of 5 %,calculate the number of kanban containers needed for the fastener.