Critical Path
The sequence of stages determining the minimum time required to complete a project, identifying tasks that directly impact the project duration.
Immediate Predecessors
The tasks or activities that must be completed directly before a specific activity can start, in a project or process sequence.
Activity Duration
The total time period required to complete a specific task or activity within a project, from start to finish.
PERT Network
A project management tool used to schedule, organize, and coordinate tasks within a project, PERT stands for Program Evaluation and Review Technique and it visually illustrates a project’s timeline and the dependencies between tasks.
Q4: Which one of the following factors is
Q4: The primary reason for the success of
Q5: The evidence from Franchthi Cave suggests that<br>A)
Q6: A teacher tells his class, "For tomorrow's
Q7: Frank is a good student. He attributes
Q9: Three of the following are strategies that
Q9: Which of the following most accurately describes
Q28: Lucy sees a boy who looks very
Q30: Which one of the following teaching practices
Q66: Which one of the following statements describes