Consider a Capital Budgeting Example with Five Projects from Which

question 2

Short Answer

Consider a capital budgeting example with five projects from which to select. Let xi = 1 if project a is selected, 0 if not, for i = 1, 2, 3, 4, 5. Write the appropriate constraint(s) for the following condition: If project 3 is chosen, project 4 must be chosen.