A production of 300 units of Twiddle Bugs, an educational toy for children, must be completed within 1 week by BugU Manufacturing. Two production lines are available, each for 30 hours during the week. Production line 1 can produce five units per hour and production line 2 can produce four units an hour. Line 1 costs $50 per hour to operate and line 2 costs $55 per hour. Overtime is available for line 1 at $15 per hour and for line 2 at $12 per hour. Management goals in decreasing order are:
P1: Produce 300 units.
P2: Maximum allowable overtime of 6 hours for line 1.
P3: Cost of overtime must not exceed $750.
P4: Avoid the underutilization of either production line. Assign weights that are proportional to their production capability.
P5: Producing more than 300 units is 1-1/2 times as undesirable as producing under 300 units.
-What are the constraints for this problem?
Global Mind-Set
An attitude or approach that considers the full spectrum of global and multicultural factors in decision-making and strategizing.
Country Contexts
The unique combination of social, economic, political, and cultural factors that characterize each country and influence business operations and strategies.
Global Leadership Ability
The capability to influence and guide individuals or groups from different countries towards achieving organizational goals.
Expatriate
An individual living and working in a country other than their country of citizenship, often temporarily and for work reasons.
Q7: If the optimal assignments include manuscript 1
Q14: Which of the following will not decrease
Q48: Determine the shortest route for a carpet
Q63: Consider the network shown in the figure.
Q66: What is the average time a customer
Q76: How much longer is the total arc
Q82: Project _ is a method for shortening
Q102: In a mixed integer model, the solution
Q106: _ is a measure of the dispersion
Q112: Consider the following decision tree. <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2836/.jpg"