Given the following information for a project, draw the AOA (Activity-On-Arrow) project network.
 Activity  Immediate  Processor  Activity Time  (days)  A 6 B 8 C  A, B 5 D  B 4 E  C 7 F  C, D 3 G  D 6 H  E, F, G 5\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Processor }\end{array} & \begin{array} { c } \text { Activity Time } \\\text { (days) }\end{array} \\\hline \text { A } & - & 6 \\\hline \text { B } & - & 8 \\\hline \text { C } & \text { A, B } & 5 \\\hline \text { D } & \text { B } & 4 \\\hline \text { E } & \text { C } & 7 \\\hline \text { F } & \text { C, D } & 3 \\\hline \text { G } & \text { D } & 6 \\\hline \text { H } & \text { E, F, G } & 5 \\\hline\end{array}


Definitions:

Developmental Processes

The series of changes and growth that occur throughout the life cycle of living organisms, especially humans.

Middle Childhood

A developmental stage that occurs approximately between the ages of 6 and 12 years, characterized by significant growth in cognitive, emotional, and social abilities.

Effortful Control

The ability to regulate one’s emotions and actions through effort, not simply through natural inclination.

Impulses

Sudden desires or urges that lead to immediate action without conscious thought.

Related Questions