Consider the following network.
Consider the following network.    -Assume that the variance for each activity in the network is equal to 1. Compute the probability that path A-B-E-F will be completed in 15 days.
-Assume that the variance for each activity in the network is equal to 1. Compute the probability that path A-B-E-F will be completed in 15 days.