Consider the Following Project -Determine the Critical Path

question 74

Multiple Choice

Consider the following project.
 Activity  Immediate  Processor  Activity Time  (days)   A 6 B 8 C  A, B 5 D  B 4 E  C 7 F  C, D 3 G  D 6 H  E, F, G 5\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Processor }\end{array} & \begin{array} { c } \text { Activity Time } \\\text { (days) }\end{array} \\\hline \text { A } & - & 6 \\\hline \text { B } & - & 8 \\\hline \text { C } & \text { A, B } & 5 \\\hline \text { D } & \text { B } & 4 \\\hline \text { E } & \text { C } & 7 \\\hline \text { F } & \text { C, D } & 3 \\\hline \text { G } & \text { D } & 6 \\\hline \text { H } & \text { E, F, G } & 5 \\\hline\end{array}
-Determine the critical path.


Definitions:

Compensation Structure

The system of pay and benefits used by an organization to reward its employees.

Prestigious

Describes something esteemed or honored, often associated with high status or quality.

Dangerous

Refers to something that is likely to cause harm or poses a risk to safety.

Desirable Location

A geographic area considered attractive for living or business activities due to various factors such as accessibility, environment, or economic opportunities.

Related Questions