Consider the following project.
 Activity  Imunediate  Predecessor  Activity Time  (drys)   A 3B4CA4DA6EB5FC,D4GEFF7\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Imunediate } \\\text { Predecessor }\end{array} & \begin{array} { c } \text { Activity Time } \\\text { (drys) }\end{array} \\\hline \text { A } & - - & 3 \\\hline \mathrm { B } & - - & 4 \\\hline \mathrm { C } & \mathrm { A } & 4 \\\hline \mathrm { D } & \mathrm { A } & 6 \\\hline \mathrm { E } & \mathrm { B } & 5 \\\hline \mathrm { F } & \mathrm { C } , \mathrm { D } & 4 \\\hline \mathrm { G } & \mathrm { E } _ { \mathrm { F } } \mathrm { F } & 7 \\\hline\end{array}
-What is the minimum possible time for completing this project?


Definitions:

Just-In-Time Manufacturing

A production strategy that aims to reduce in-process inventory and associated carrying costs by producing goods only as they are needed.

Globalization

The evolution of an integrated and interdependent world economy.

Big Data

Large and complex data sets that require advanced tools and methodologies for analysis, processing, and storage.

Data Analysis

The process of examining, cleansing, transforming, and modeling data with the goal of discovering useful information, informing conclusions, and supporting decision-making.

Related Questions