Consider the following project.
 Activity  Imunediate  Predecessor  Activity Time  (drys)   A 3B4CA4DA6EB5FC,D4GEFF7\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Imunediate } \\\text { Predecessor }\end{array} & \begin{array} { c } \text { Activity Time } \\\text { (drys) }\end{array} \\\hline \text { A } & - - & 3 \\\hline \mathrm { B } & - - & 4 \\\hline \mathrm { C } & \mathrm { A } & 4 \\\hline \mathrm { D } & \mathrm { A } & 6 \\\hline \mathrm { E } & \mathrm { B } & 5 \\\hline \mathrm { F } & \mathrm { C } , \mathrm { D } & 4 \\\hline \mathrm { G } & \mathrm { E } _ { \mathrm { F } } \mathrm { F } & 7 \\\hline\end{array}
-Compute the slack time for activity C.


Definitions:

Statute of Limitations

Laws that set the maximum time after an event within which legal proceedings may be initiated, after which the claims are prohibited.

Litigation File

A collection of documents and records related to a legal case, maintained by a law firm or legal department for reference and case management.

Compel Discovery

A legal process where a court orders one party to provide evidence or information to the other party in a lawsuit.

Discovery Request

A formal request by one party in litigation to the other party for information or documents relevant to the case.

Related Questions