A PERT/CPM Activity Has an Optimistic Time Estimate of 3

question 115

Multiple Choice

A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is: