Refer to the Table Below to Answer the Question(s) That

question 109

Short Answer

Refer to the table below to answer the question(s) that follow:
                         Activity                                 Times (weeks) Activity  Predecessor  Optimistic  Most Likely  Pessimi  A 91521 B 132123 C  A 6918 D  A 233547 E  B 192627 F  C 232941 G  D,E 142026 H  F,G 258~~~~~~~~~~~~~~~~~~~~~~~~~Activity~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Times~ (weeks)\\\begin{array}{c}\text { Activity } & \text { Predecessor } & \text { Optimistic } & \text { Most Likely } & \text { Pessimi } \\\hline \text { A } & --- & 9 & 15 & 21 \\\text { B } & --- & 13 & 21 & 23 \\\text { C } & \text { A } & 6 & 9 & 18 \\\text { D } & \text { A } & 23 & 35 & 47 \\\text { E } & \text { B } & 19 & 26 & 27 \\\text { F } & \text { C } & 23 & 29 & 41 \\\text { G } & \text { D,E } & 14 & 20 & 26 \\\text { H } & \text { F,G } & 2 & 5 & 8\end{array}
-What is the probability that the critical path for this project will be completed within 75 weeks?


Definitions:

Costs

The expense required for something; the money spent on or needed for a project, product, or service.

Profit-Seeking Decision Maker

An individual or entity focused on making decisions that are expected to result in the highest possible profit.

Entrepreneur

An individual who organizes and operates a business venture, taking on greater than normal financial risks in order to do so.

Business Projects

Specified endeavors undertaken by businesses to achieve specific objectives, often within a set timeline and budget.

Related Questions