Given the Following Information for a Project, Draw the AOA

question 59

Essay

Given the following information for a project, draw the AOA (Activity-On-Arrow) project network.
 Activity  Immediate  Processor  Activity Time  (days)  A 6 B 8 C  A, B 5 D  B 4 E  C 7 F  C, D 3 G  D 6 H  E, F, G 5\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Processor }\end{array} & \begin{array} { c } \text { Activity Time } \\\text { (days) }\end{array} \\\hline \text { A } & - & 6 \\\hline \text { B } & - & 8 \\\hline \text { C } & \text { A, B } & 5 \\\hline \text { D } & \text { B } & 4 \\\hline \text { E } & \text { C } & 7 \\\hline \text { F } & \text { C, D } & 3 \\\hline \text { G } & \text { D } & 6 \\\hline \text { H } & \text { E, F, G } & 5 \\\hline\end{array}


Definitions:

Selling Price

The price at which a product or service is sold to the purchaser, often determined by the cost of production, market demand, and competition.

Cost

The amount of money required to purchase something or the expense associated with creating a product or service.

Mark-up

The extra sum included in the goods' selling price to cover both overhead expenses and profit.

Selling Price

The amount of money for which a product or service is sold to a customer.

Related Questions