Given the Following Information for a Project, Identify the Critical

question 81

Essay

Given the following information for a project, identify the critical path and determine the total completion time of the project.
 Activity  Immediate  Processor  Activity Time  (days)  A 6 B 8 C  A, B 5 D  B 4 E  C 7 F  C, D 3 G  D 6 H  E, F, G 5\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Processor }\end{array} & \begin{array} { c } \text { Activity Time } \\\text { (days) }\end{array} \\\hline \text { A } & - & 6 \\\hline \text { B } & - & 8 \\\hline \text { C } & \text { A, B } & 5 \\\hline \text { D } & \text { B } & 4 \\\hline \text { E } & \text { C } & 7 \\\hline \text { F } & \text { C, D } & 3 \\\hline \text { G } & \text { D } & 6 \\\hline \text { H } & \text { E, F, G } & 5 \\\hline\end{array}


Definitions:

Particular Needs

Specific requirements or desires of individuals or groups that need to be addressed or fulfilled.

Stereotype

A widely held but fixed and oversimplified image or idea of a particular type of person or thing, often based on limited information.

Performance

The manner in which an individual, group, or entity executes and accomplishes tasks, goals, or activities, often measured against a standard.

Behaviour

The actions or reactions of an entity (usually an individual) in response to external or internal stimuli.

Related Questions