The university is scheduling cleaning crews for its ten buildings. Each crew has a different cost and is qualified to clean only certain buildings. There are eight possible crews to choose from in this case. The goal is to minimize costs while making sure that each building is cleaned. The management science department formulated the following linear programming model to help with the selection process.
Min 200x1 + 250x2 + 225x3 + 190x4 +215x5 + 245x6 + 235x7 + 220x8
s.t. x1 + x2 + x5 + x7 ? 1 {Building A constraint}
X1 + x2 + x3 ? 1 {Building B constraint}
X6 + x8 ? 1 {Building C constraint}
X1 + x4 + x7 ? 1 {Building D constraint}
X2 + x7 ? 1 {Building E constraint}
X3 + x8 ? 1 {Building F constraint}
X2 + x5 + x7 ? 1 {Building G constraint}
X1 + x4 + x6 ? 1 {Building H constraint}
X1 + x6 + x8 ? 1 {Building I constraint}
X1 + x2 + x7 ? 1 {Building J constraint}
Which of the crews can be scheduled to clean buildings B and F?
Debt Ratio
A financial metric comparing the total debt of a company to its total assets, indicating the proportion of a company's assets that are financed by debt.
Q11: In most cases, the minimum acceptable level
Q17: In a maximum flow problem, flow is
Q34: Once the data is entered into a
Q35: Management science is based strongly on which
Q42: After some experimentation, you have determined that
Q43: Refer to the following payoff table:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6598/.jpg"
Q55: Which of the following can be part
Q60: A grocery store manager must decide how
Q62: Which of the following distributions is not
Q71: A smoothing constant of 0.1 will cause