The university is scheduling cleaning crews for its ten buildings. Each crew has a different cost and is qualified to clean only certain buildings. There are eight possible crews to choose from in this case. The goal is to minimize costs while making sure that each building is cleaned. The management science department formulated the following linear programming model to help with the selection process.
Min 200x1 + 250x2 + 225x3 + 190x4 +215x5 + 245x6 + 235x7 + 220x8
s.t. x1 + x2 + x5 + x7 ? 1 {Building A constraint}
X1 + x2 + x3 ? 1 {Building B constraint}
X6 + x8 ? 1 {Building C constraint}
X1 + x4 + x7 ? 1 {Building D constraint}
X2 + x7 ? 1 {Building E constraint}
X3 + x8 ? 1 {Building F constraint}
X2 + x5 + x7 ? 1 {Building G constraint}
X1 + x4 + x6 ? 1 {Building H constraint}
X1 + x6 + x8 ? 1 {Building I constraint}
X1 + x2 + x7 ? 1 {Building J constraint}
Which of the crews can be scheduled to clean buildings B and F?
Motivating
The process of stimulating interest or enthusiasm in someone to inspire them to take action or engage in a specific behavior.
Workplace
The place or environment where people work, including offices, factories, or any physical or virtual space.
Need
A requirement or necessity for survival and well-being.
McClelland's
A theory of motivation that highlights the importance of three primary needs: the need for achievement, the need for affiliation, and the need for power.
Q6: The figure below shows the possible routes
Q6: Financial planning is one of the most
Q7: One way to ensure that Analytic Solver
Q16: Linear regression can be used to approximate
Q38: After some experimentation, you have determined that
Q40: A mathematical model of a business problem
Q45: Judgmental forecasting methods have been developed to
Q48: Based on the following payoff table,
Q52: A time-series is said to be smooth
Q63: One reason that a manager may choose