A Firm Has Prepared the Following Binary Integer Program to Evaluate

question 25

Multiple Choice

A firm has prepared the following binary integer program to evaluate a number of potential new capital projects. The firm's goal is to maximize the net present value of their decision while not spending more than their currently available capital.
Max 100x1 + 120x2 + 90x3 + 135x4
s.t. 150x1 + 200x2 + 225x3 + 175x4 ? 500 {Constraint 1}
X1 + x2 + x3 + x4 ? 2 {Constraint 2}
X2 + x4 ? 1 {Constraint 3}
X2 + x3 ? 1 {Constraint 4}
X1 = x4 {Constraint 5} xj={1, if project j is selected 0, otherwise x _ { j } = \left\{ \begin{array} { l } 1 , \text { if project } j \text { is selected } \\0 , \text { otherwise }\end{array} \right.
Which of the constraints enforces a contingent relationship?

Recognize the significance of marriage and its functions in society.
Analyze the effects of changing family dynamics on children and societal institutions.
Understand the historical context and evolution of family forms.
Explore the debates surrounding the necessity and impact of sociopolitical reforms on family life.

Definitions:

Core Developers

The main group of programmers or developers responsible for developing and maintaining a software project or platform.

Communities

Communities refer to groups of people who share common interests or goals and interact within a shared context or platform, ranging from physical neighborhoods to virtual spaces online.

Code Changes

Modifications or updates made to a software's source code to add new features, fix bugs, or improve performance.

Errors

Mistakes or discrepancies that occur in computational processes, programs, or calculations.

Related Questions