Although the contract called for the delivery of three manuals, the writer had put so much effort into the first two that the buyer agreed to pay the whole contract price, $3,000, for the two instead of the three manuals. Which of the following stops the buyer from later suing the writer for breach of contract and demanding the completion of the third manual?