If the Following Jobs Are Sequenced According to the DDATE

question 93

Multiple Choice

If the following jobs are sequenced according to the DDATE rule then the mean completion time (in days) for all jobs is (assume zero for today's date) If the following jobs are sequenced according to the DDATE rule then the mean completion time (in days)  for all jobs is (assume zero for today's date)    A)  16.4 days. B)  22.6 days. C)  28.7 days. D)  33.0 days