If the Following Jobs Are Sequenced According to the DDATE

question 60

Multiple Choice

If the following jobs are sequenced according to the DDATE rule then the maximum job tardiness (in days) is (assume zero for today's date) If the following jobs are sequenced according to the DDATE rule then the maximum job tardiness (in days)  is (assume zero for today's date)    A)  12 days. B)  15 days. C)  16 days. D)  27 days.