A project consists of the following activities:
A project consists of the following activities:    Table XX -Using Table XX,the earliest finish (EF) time for activity D is A) 7 weeks. B) 13 weeks. C) 20 weeks. D) 30 weeks. Table XX
-Using Table XX,the earliest finish (EF) time for activity D is