Examlex

Solved

A Project Consists of the Following Four Activities with Activity

question 33

Multiple Choice

A project consists of the following four activities with activity times in days:
A project consists of the following four activities with activity times in days:    Table YY -Using Table YY,the earliest start (ES) time for activity B is A) 5 days. B) 6 days. C) 11 days. D) 14 days. Table YY
-Using Table YY,the earliest start (ES) time for activity B is