A project consists of the following four activities with activity times in days:
A project consists of the following four activities with activity times in days:    Table CC -Using table CC,what is the total allowable crash time for activity B? A) 5 B) 1 C) 2 D) 0 Table CC
-Using table CC,what is the total allowable crash time for activity B?