An assembly line has been designed to make battery-powered beverage mixers.Task details are shown in the table below:
a.What is the assigned cycle time (in minutes)?
b.What is the maximum output rate of this line in mixers per hour?
c.What is the total idle time per cycle?
d.What is the assembly line's efficiency?
Delivery Cycle Time
Delivery cycle time is the total time taken from the receipt of a customer order to the delivery of the product, indicating the efficiency of a company's production and distribution process.
Fill Orders
The process of completing customer orders by preparing and delivering the requested goods or services.
Manufacturing Cycle Efficiency
A measure of the efficiency of the production process, calculated as the value-added time divided by the total cycle time.
Delivery Performance
A measurement of how well a company can meet its promised delivery times to customers.
Q3: Net present value will be greater:<br>A)as a
Q21: A process that is assumed to be
Q21: The transportation model calculates an optimal shipping
Q57: One difference in the stepping-stone method compared
Q58: A grocery chain is deciding on where
Q70: A decision maker using the maximin criterion
Q92: Using the factor ratings shown below,determine which
Q93: In assembly-line balancing,the theoretical minimum number of
Q94: Break-even is the number of units at
Q103: The transportation model,when applied to location analysis:<br>A)minimizes