Two Critical Path Activities Are Candidates for Crashing on a CPM

question 2

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) One; $400 B) One; $6,800 C) Two; $1,000 D) Two; $5,000 E) One or Two should be crashed; $1,400


Definitions:

Intellectual

Relating to the ability to think and understand ideas and information at a complex level.

Creative

The quality or ability to create or invent something original and valuable.

Cross-sectional Studies

Research that analyzes data from a population, or a representative subset, at a specific point in time to examine relationships between variables.

Cohort Effects

Differences among people that stem from being born at different times or periods, leading to distinctive formative experiences.

Related Questions