Two Critical Path Activities Are Candidates for Crashing on a CPM

question 116

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) B; $2,000 B) B; $8,000 C) C; $1,000 D) C; $2,000 E) C; $6,000


Definitions:

Sociological Observations

The practice of examining social behaviors, interactions, and patterns to understand how societies function and evolve.

Theoretical Abstractions

Concepts or models that simplify complex realities to facilitate understanding or analysis.

Economic Situation

The state of economic conditions and variables in a specific region or globally at a particular time, including factors like GDP growth, employment rates, inflation, and market stability.

Class

A system of ordering society whereby people are divided into sets based on perceived social or economic status.

Related Questions