Activity R on a CPM Network Has Predecessors M and N,and

question 103

Multiple Choice

Activity R on a CPM network has predecessors M and N,and has successor S.R has duration 5.N's late finish is 18,while M's is 20.S's late start is 14.Which of the following is definitely true?