The Network Below Represents a Project Being Analyzed by the Critical

question 101

Essay

The network below represents a project being analyzed by the critical path method.Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=10,and J=6. The network below represents a project being analyzed by the critical path method.Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=10,and J=6.   a.What task must be on the critical path,regardless of activity durations? b.What is the duration of path A-B-E-H-J? c.What is the critical path of this network? d.What is the length of the critical path? e.What is slack time at activity H? f.What is the Late Finish of activity H? g.If activity C were delayed by two time units,what would happen to the project duration? a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?


Definitions:

Surgical Scrub

A thorough cleaning of the hands and arms with antimicrobial soap by surgical personnel to reduce the risk of infection.

Blood Loss

The reduction of blood volume due to injury, surgery, or medical conditions, which can range from minor to life-threatening.

Deficient Fluid Volume

A medical term that describes a decrease in the amount of fluid in the body, which can lead to dehydration and other health problems.

Bony Prominences

Areas of the body where bone is close to the skin surface, which are at higher risk of developing pressure ulcers.

Related Questions