Or an Activity in a CPM/PERT Network,if the Normal Time

question 7

Multiple Choice

or an activity in a CPM/PERT network,if the normal time is 10 weeks and the crash time is 5 weeks,and the normal cost is $2,000 and the crash cost is $5,000,the crash cost per week is