If the Following Jobs Are Sequenced According to the DDATE

question 50

Multiple Choice

If the following jobs are sequenced according to the DDATE rule then the total number of jobs that would be late is (assume zero for today's date) If the following jobs are sequenced according to the DDATE rule then the total number of jobs that would be late is (assume zero for today's date)    A) 5 jobs. B) 4 jobs. C) 3 jobs. D) 2 jobs.