A Project Consists of the Following Four Activities with Activity

question 56

Multiple Choice

A project consists of the following four activities with activity times in days:
A project consists of the following four activities with activity times in days:    Table YY -Using Table YY,the time to complete the entire project would be A) 23 days. B) 19 days. C) 17 days. D) 11 days. Table YY
-Using Table YY,the time to complete the entire project would be