Examlex

Solved

The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

question 22

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table ZZ -Using Table ZZ,the earliest finish time for activity C is A) 5.00 weeks. B) 8.17 weeks. C) 9.50 weeks. D) 12.67 weeks. Table ZZ
-Using Table ZZ,the earliest finish time for activity C is


Definitions: