A Project Consists of the Following Four Activities with Activity

question 6

Multiple Choice

A project consists of the following four activities with activity times in days:
A project consists of the following four activities with activity times in days:    Table YY -Using Table YY,the earliest finish (EF) time for activity C is A) 4 days. B) 6 days. C) 10 days. D) 11 days. Table YY
-Using Table YY,the earliest finish (EF) time for activity C is