A Project Consists of the Following Four Activities with Activity

question 29

Multiple Choice

A project consists of the following four activities with activity times in days:
A project consists of the following four activities with activity times in days:    Table YY -Using Table YY,the critical path for this project is A) A-B-C. B) A-C-D. C) A-B-D. D) A-B-C-D. Table YY
-Using Table YY,the critical path for this project is