A Project Consists of the Following Four Activities with Activity

question 91

Multiple Choice

A project consists of the following four activities with activity times in days:
A project consists of the following four activities with activity times in days:    Table YY -Using Table YY,the amount of slack associated with activity C is A) 4 days. B) 3 days. C) 2 days. D) 1 day. Table YY
-Using Table YY,the amount of slack associated with activity C is