The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table ZZ -Using Table ZZ,the critical path for the project consists of activities A) A-B-C-D-E B) A-B-C-E C) A-B-D-E D) A-B-C-D Table ZZ
-Using Table ZZ,the critical path for the project consists of activities