A Project Consists of the Following Four Activities with Activity

question 60

Multiple Choice

A project consists of the following four activities with activity times in days:
A project consists of the following four activities with activity times in days:    Table CC -Using table CC,which of the activities has the lowest crash cost per day? A) A B) B C) C D) D Table CC
-Using table CC,which of the activities has the lowest crash cost per day?